Tuesday, 24 September 2013

000-122 free download

Question: 1

A Power 740 customer with 4 cores licensed to AIX is planning to add 4 additional cores and a partition for IBM i. They have sized the new IBM i workload at 1.7 cores and AIX will use the other 6.3 cores. What software will be necessary to enable this solution'?

A. PowerVM Standard Edition licensed for 8 cores
AIX Standard Edition licensed for 7 cores
IBM i licensed for 2 cores
B. AIX Enterprise Edition licensed for 6 cores
IBM i licensed for 2 cores
C. PowerVM Express Edition licensed for 8 cores
AIX Express Edition licensed for 7 cores
IBM i licensed for 2 cores
D. PowerVM Standard Edition licensed for 8 cores
AIX Standard licensed for 6.3 cores
IBM i licensed for 1.7 cores

Answer: A    

Question: 2

A customer has let their Software Maintenance (SWMA) expire and needs to activate additional processors on their Power 770. What does the customer need to purchase?

A. Additional licenses for the new processors.
B. New licenses for the both the existing and new processors.
C. After License Fee for both the new and the old processors.
D. Additional licenses for the new processors and After License Fee for the existing processors.

Answer: D    

Question: 3

A sales professional is engaged in a competitive sales situation against a non-IBM solution that is unfamiliar to them. Which resource should be engaged first?

A. CompeteLine
B. Migration Factory
C. TCO analysis tools
D. Pre Sales Advisor tool

Answer: A    

Question: 4

A customer has several dedicated LPARs. The key application in one LPAR temporarily needs more processing power. How can performance be improved?

A. Mirror the LPAR to a second system
B. Add a second LPAR to the application
C. Change dedicated LPARs to shared LPARs
D. Reduce the number of LPARs on the system

Answer: C    

Question: 5

Which of the following can be used to provide a basis for proving that Power Systems have a lower cost of ownership than x86 systems?

A. rPerf and CPW measurements
B. Analysis report from the Alinean Tool
C. ISV recommendations and lower IBM financing costs
D. White papers that illustrate IBM's leadership technology

Answer: B